GROUP: |
Building |
TYPE: |
Swimming-Pool/Spa |
SUB-TYPE: |
Apartment |
PRIMARY USE: |
(4) Pool/Spa - Public |
WORK DESCRIPTION: |
(N) POOL (IRR 42'-4" X 18'-4") PER LA CITY STD PLAN #268 |
PERMIT ISSUED: |
Yes |
PERMIT ISSUE DATE: |
03/14/2014 |
ISSUING OFFICE: |
Van Nuys |
CURRENT STATUS: |
Permit Finaled |
CURRENT STATUS DATE: |
09/09/2014 |
|
|
Submitted |
09/30/2013 |
APPLICANT |
Assigned to Plan Check Engineer |
10/24/2013 |
NILOOFAR MEHRAIN |
Disabled Access Plans Picked Up |
10/28/2013 |
APPLICANT |
Corrections Issued |
10/29/2013 |
NILOOFAR MEHRAIN |
Quality Review Completed |
11/04/2013 |
TAMERA SVETICH |
Building Plans Picked Up |
11/05/2013 |
APPLICANT |
Applicant returned to address corrections |
03/06/2014 |
NILOOFAR MEHRAIN |
Plan Check Approved |
03/14/2014 |
NILOOFAR MEHRAIN |
Issued |
03/14/2014 |
LADBS |
Permit Finaled |
09/08/2014 |
SAKO AGHAZARIAN |
Eng Process Fee Ord 176,300 |
Cleared |
11/06/2013 |
JOHN LIN |
Sewer availability |
Cleared |
11/06/2013 |
JOHN LIN |
Public Works-Highway Ded. |
OK for CofO |
11/06/2013 |
JOHN LIN |
Public Works-Open Permits |
OK for CofO |
11/06/2013 |
JOHN LIN |
Public Works-Sewers |
OK for CofO |
11/06/2013 |
JOHN LIN |
"D" conditions |
Cleared |
11/12/2013 |
RONY GIRON |
"Q" conditions |
Cleared |
11/12/2013 |
RONY GIRON |
"T" removal |
Cleared |
11/12/2013 |
RONY GIRON |
APC |
Cleared |
11/12/2013 |
RONY GIRON |
CPC |
Cleared |
11/12/2013 |
RONY GIRON |
City Hist. Cultural Monument |
Cleared |
11/12/2013 |
RONY GIRON |
HPOZ |
Cleared |
11/12/2013 |
RONY GIRON |
Historic monument |
Cleared |
11/12/2013 |
RONY GIRON |
Historical monument |
Cleared |
11/12/2013 |
JIM URQUHART |
Miscellaneous |
Cleared |
11/12/2013 |
RONY GIRON |
Project located in CRA area |
Cleared |
11/12/2013 |
JIM URQUHART |
Tract Map conditions |
Cleared |
11/12/2013 |
RONY GIRON |
ZA Case |
Cleared |
11/12/2013 |
RONY GIRON |
Grading Pre-Inspection |
Cleared |
11/13/2013 |
PATRICK MISCHLICH |
Title 19 building approval |
Cleared |
12/11/2013 |
BEN REYES |
Public Swimming Pool approval |
Cleared |
03/06/2014 |
LACDHS APPROVED |
ZI |
Cleared |
03/07/2014 |
MARITZA PRZEKOP |
DAS Clearance |
Cleared |
03/11/2014 |
NILOOFAR MEHRAIN |
|